Howse Renovations
May 6th, 2024
MCH RENOVATION PROGRESS
Get ready to witness some major transformations happening right before our eyes. From shiny new classrooms to sparkling corridors and from state-of-the-art facilities to vibrant learning spaces, our school is about to undergo a stunning renovation that will leave us all in awe! Not to mention over 35 additional parking spaces!π
I will keep you posted with updates and photos over the next 2 years in this Howse Renovation special newsletter.
Just imagine the endless possibilities that await us in our beautifully renovated school! π This is not just a makeover; it's a transformation that will elevate our learning environment and inspire us to reach new heights of excellence.
RENOVATION TIMELINE
There's 5 Phases of the Renovation Process
Phase 1A: Summer 2024 - Parking lot, 3 Classrooms, Library, and new Design Lab
Phase 1B: During the 24-25 school year - Classroom addition
Phase 2: Summer 2025 - Classrooms and restrooms in the center hallways
Phase 3: Fall 2025 - 6 Classrooms
Phase 4: Spring 2026 - 5 Classrooms
Phase 5: Summer 2026 - Cafeteria, Gym, and Office Area.
10 IMPORTANT THINGS TO KNOW
- The safety of the students and staff is the top priority during construction!ππ·π·π»ββοΈ
- AC gets turned on at the end of renovation in summer 2026. There wonβt be appropriate electric to operate the chiller before then.
Kindergarten staying at MCH during construction. π
Construction workers will have to obtain the same clearances as WCASD employees. They will enter and exit from outside doors as much as possible.
A new parking lot will be built this summer, adding 35 new parking spaces and allowing a new flow for the carline. Additional staff will be here on the first day of school to help direct traffic.ππ
Interior locked plywood barrier will be used to increase safety. Construction workers will have badges.π§
Trees removed during construction, but we will replaced.π³
Students won't be exposed to additional dust and debris during construction. The WCASD uses the highest-quality filters for internal air quality, and the filters will be changed frequently.
Email Principal Pavlo with all construction questionsπ¬
Change during construction can be stressful. Our Dragon family needs to stay strong and support each other.πππͺ
May 6, 2024 Parent Meeting to Share Plans
Presentation by: Wayne Birster, Director of Facilities & Operations; Damon Gonzaga, Capital Projects Manager; Sara Missett, Director of Elementary Ed; David Christopher, Superintendent; Jackie Pavlo, Principal
Approx. 40 parents were in attendance.
The team discussed the 10 Important Facts above, and here are a few more fun facts:
- MCH is staying a single-floor school
- As rooms are renovated, the classroom will receive a new room number.
- No new Kindergarten play area will be built
- Along with going over maps of the construction phases, (for security reason, we will not post the maps) we saw the chosen colors to make our Howse light up!