Project Updates - February 2024
Construction Completed Last Month
- Started Framing on the High School side
- Completed wall framing on the Middle School side
- Installed glulam beams and started roof framing on the Middle School Side
- Started electrical rough-in
- Ongoing placement of structural steel
Construction Work Planned for This Month
- Continue framing on the High School side
- Install glulam beams and start roof framing on the High School Side
- Roof framing will be completed on the Middle School side and start on the High School side
- Ongoing electrical and plumbing rough-in
Project Overview
- Project Scope: The primary purpose of this project is to build eight permanent high-quality science labs for both the Middle and High Schools. This project was identified in the Facilities Master Plan as a Critical Needs Project. Support spaces include science teacher workrooms and student and staff restrooms. By the end of the project, nine portables will be removed from the campuses.
- Architect: DSK Architects
- Contractor: Soltek Pacific Construction
- Anticipated Completion: Summer 2024