Indian Trail Facilities Update
7/1/2024
From the Desk of Dr. Jacobs ...
Hello Indian Trail Families! I attended our biweekly construction update on our track. Here are a few relevant points that were covered:
- Grading begins on the track today
- More rock will be added as needed
- Long jump pits are complete
- Shot and discus pads are complete
- Fill dirt ready to level staging areas close to the baseball outfield
- Rerouted walking trail for the public is taking shape
- All electrical boxes, communication connections, and drainage systems complete
- Paving the 8 lane track is to begin in two weeks
- Completion date: October 4th
Thanks to the construction team for keeping us up to date!
Dr. James Jacobs
Future walking trail and sidewalk on Lambeth.
2 Long jump pits on the Lambeth side of the track.
Grade the 8 lane track
Charlee Memorial Update! 💜
Back in May, our school committee made up of students, teachers, and parents created a design honoring Charlee Blackburn , Anna Love, and Teddy Hartsaw. General Shale Brick is bringing that design to life!