HSSD Construction Update
June 2024
This publication showcases construction progress across the district. The projects listed are the result of the successful April 2021 referendum, in which residents voted to approve $98 million in facilities updates at all eight HSSD schools. We are grateful for the community's support! Please visit our Facilities Update website to learn more.
- Old lockers are being removed and new lockers are being installed.
- With students home for the summer, ceiling removal has begun in the choir and band rooms.
- Furniture installers have been working on assembling and installing new classroom furniture.
Interior of building: Construction has started and will be complete for the start of next school year.
- Cafeteria remodel - New flooring, painting, new acoustical treatments.
- Classrooms and hallways near the library - New flooring, lighting, door hardware, and ceilings.
- Throughout the entire building - Completion of HVAC upgrades and installation of air conditioning.
Exterior of building: Construction will start at the end of June (weather dependent) and will be complete for the start of next school year.
- Reconstruction of west parking lot - New asphalt, site drainage, and sidewalks.
- Replace the main playground structure and install new wood chips.
Roof replacement: Start at the beginning of July (weather dependent) and be complete by the end of July.
- Replace the roof over the library and near the gym.
What Else is Happening this Summer?
- Roof replacements at Bay View and Lineville.