Project Updates - September 2024
Construction Completed Last Month
- Plaster
- Exterior Paint
- Deconstruct scaffolding
- Waterproof footings
- Drill pier footings for canopy columns
- Installation of electrical trims/finishes
- Energize building
- Installation of fire sprinkler heads
- Installation of restroom partitions
- Complete remaining underground site utilities
- Asphalt paving
Construction Work Planned for This Month
- Install gutter and parapet flashing
- Install columns and frame large canopies
- Start up HVAC units
- Install casework and sinks
- Install flooring
- Continue drainage at seat walls
- Install artificial turf and sidewalks
Project Overview
- Project Scope: The primary purpose of this project is to build eight permanent high-quality science labs for both the Middle and High Schools. This project was identified in the Facilities Master Plan as a Critical Needs Project. Support spaces include science teacher workrooms and student and staff restrooms. By the end of the project, nine portables will be removed from the campuses.
- Architect: DSK Architects
- Contractor: Soltek Pacific Construction
- Anticipated Completion: Fall / Winter 2024
Join the CBOC!
We are accepting applications to join the Citizens' Bond Oversite Committee (CBOC). The CBOC reviews bond-funded school projects and informs the public about bond expenditures and uses.
Sign up here: bit.ly/CBOCWCCUSD23
Project Website
Additional information and past newsletters can be found on the project website. To receive an email of this monthly newsletter or ask a project question, please email: askfacilities@wccusd.net