Hercules CNP
August 2024
Project Updates - August 2024
Construction Completed Last Month
- Roofing completed
- Ongoing installation of cloud ceilings in high school classrooms
- Application of the plaster finish coat
- Ongoing installation of the tile in restrooms
- Ongoing demolition of classroom portables
- Connecting the fire water and sewer lines
Construction Work Planned for This Month
- Exterior Paint
- Removal of the scaffolding after the stucco is applied
- Completion of T-bar ceiling grids
- Installation of restroom partitions
- Installation of electrical trims/finishes
- Field measurement for the casework
- Asphalt paving
- Installation of artificial turf at seat walls
Project Overview
- Project Scope: The primary purpose of this project is to build eight permanent high-quality science labs for both the Middle and High Schools. This project was identified in the Facilities Master Plan as a Critical Needs Project. Support spaces include science teacher workrooms and student and staff restrooms. By the end of the project, nine portables will be removed from the campuses.
- Architect: DSK Architects
- Contractor: Soltek Pacific Construction
- Anticipated Completion: Fall / Winter 2024
Project Website
Additional information and past newsletters can be found on the project website. To receive an email of this monthly newsletter or ask a project question, please email: askfacilities@wccusd.net