Blue River Valley Schools
December 13, 2024
Under Construction at BRV
Elementary Renovation
Phase 1 should be complete over Winter Break!
Phase 1 of construction includes the middle section of the building and two classrooms near the cafeteria that previously housed art and music. This phase is expected to be completed by mid-December, with final touches planned for over Christmas break.
The next phase will focus on half of Pod B and half of Pod C. As part of this phase, every classroom in the pods, as well as the restrooms and workrooms, will undergo a complete renovation, marking another exciting step forward in the transformation of the building.
Progress Pictures from December 3rd
District Office
Construction on the district office and maintenance areas is progressing well and remains on track for completion in February. The district office is taking shape, with new walls going up to define the space. Once completed, the office will feature four small offices, a reception area, restrooms, a small workroom, and a conference room.
The maintenance area will include dedicated space for deliveries and storage, ensuring greater efficiency for our operations.
We’re thrilled to see this phase of the project coming together and deeply appreciate the community’s continued support as we work to enhance our facilities for the benefit of students, staff, and families.
Business Manager's Office
Superintendent's Office
Director of Student Services' Office
District Office Conference Room
District Office Hallway Entrance
Maintenance Room
Important Dates
- December 20 - End of 2nd Quarter and 1st Semester
- December 21-January 5 - Winter Break
- January 6 - Teacher Record Day AM
- January 7 - Students Return
- January 13 - January School Board Meeting at 7:00 PM
- January 20 - Martin Luther King Jr. Day - No School