CONSTRUCTION UPDATE
Crescent Harbor Elementary I December 2024
Crescent Harbor Elementary construction has progressed throughout December. We can now see the outline of the building. Mr. Weinsheimer enjoyed seeing his new office space, and all of the complicated plumbing and electrical wires are almost complete. Thank you Tiger Construction.
Here's what it looks like on site:
The final brace frame footing concrete pour took place the day before Thanksgiving!
Miscellaneous concrete footing pours continue each week.
These photo shows the complicated nature of all the underground coordination needed between plumbing, electrical and concrete trades.
This photo shows the capillary break pea gravel being placed via telebelt in the next section of the building.
The green vaper barrier and the welded wire mesh is installed in preparation for the next concrete slab pour.
The elevator pit concrete has all been poured.
The elevator brace frame.
Underground plumbing work is progressing very well!
Brace frame structural steel has arrived on site.
Underground storm drain piping installation started last week.
Mr. Weinsheimer standing in the new gym, minus the basketball!
This photo shows the underground piping for the new kitchen. The black pipes are the hot water pipes.
Mr. Weinsheimer standing in his new office.
The photos shows the entrance of the new school.