October 23, 2024
Under Construction at BRV
Elementary Renovation
Phase 1 of construction is the middle part of the building and the two classrooms (that were art and music) in the cafeteria. It is amazing how much I can forget what the area used to be once the walls have been removed! This phase is predicted to be complete in the middle of December.
Progress Pictures
Teacher's Lounge and two flex offices. This was the music room. A music room will move to another classroom near the cafeteria and be completed in a later phase.
Art Room. This was the art room.
Robotics Area and STEM Lab. This was a middle part of the building that had spaces like the teacher's lounge, special education offices, etc.
Media Center North Wall
Media Center South Wall
Media Center New Southwest Entrance
District Office
I am aware that finding a long-term solution to the band area is a high priority in our district. I have attended several meetings about the long-term facility plans at BRV which includes a dedicated space for the band. It is not perfect, but there will be a music and band room at the elementary when construction is complete with our current renovation projects. I am working on creating a 5-year facility plan to include improvements such as the fine arts area, parking lots, the middle area of the jr./sr. high school, the elementary cafeteria, etc. As those plans are developed in the next 6-9 months I will share them at regular board meetings and in future newsletters.
District Office. You can see the exterior entrance door to the left in the picture.
District Office. This picture includes a look at the small conference room and this space will turn into future district staff offices.
Elementary Cafeteria Serving Line
The serving line in the elementary cafeteria needed to be replaced as it was beyond repair. Over fall break the new serving line was installed. We were able to use leftover money from our tennis court project to purchase the updated equipment for our elementary students and cafeteria staff.
Tennis Courts are Almost Complete
The tennis courts needed some maintenance over Fall Break. Over the years we will need to perform maintenance and upkeep on the playing surface. We should not need to resurface the tennis courts for 5-7 years. We have also been working with Henry County REMC to prepare for a small amount of electricity to be put in. Tennis season is over, but many nights I see people practicing on the tennis courts from our community. We hope you continue to enjoy this space well into the future!
Important Dates
- October 25 - Waiver Day - No School or E-Learning for Students & Parent/Teacher Conferences
- November 11 - BRV Veteran's Day Convocation 9:00 AM in Shelton Gym
- November 11 - Regular School Board Meeting 7:00 in the Media Center
- November 13 - Waiver Day - No School or E-Learning for Students
- November 27-29 - Thanksgiving Break - No School