Project Updates - July 2024
Construction Completed Last Month
- Complete the installation of drywall
- Completion of interior painting
- Ongoing installation of roofing
- Ongoing preparation and installation of the exterior stucco
- Ongoing installation of the tile in restrooms
- Ongoing installation of the ceiling grid
Construction Work Planned for This Month
- Demolition of 1 restroom 4 classrooms portables
- Site utility connections
- Field measurement for the casework
- Begin preparation for flooring
- Removal of the scaffolding after the stucco is applied
Project Overview
- Project Scope: The primary purpose of this project is to build eight permanent high-quality science labs for both the Middle and High Schools. This project was identified in the Facilities Master Plan as a Critical Needs Project. Support spaces include science teacher workrooms and student and staff restrooms. By the end of the project, nine portables will be removed from the campuses.
- Architect: DSK Architects
- Contractor: Soltek Pacific Construction
- Anticipated Completion: Fall / Winter 2024