Riverside ES Critical Needs Project
August 2023
Project Updates - August 2023
Construction Completed Last Month
- Grading
- Installing storm drain lines
- Installation of the new play structures
- New blacktop asphalt and striping
- New garden
Upcoming Activities
- Curing of the safety surface under the play structures and final inspection
- Installation of site benches
Project Overview
- Project Scope: Adjusting the primary playground to relocate the kindergarten playground and garden, which were displaced during the soil stabilization project. The project includes the installation of two play structures, and repair/replacement of the blacktop surface, and constructing a garden.
- Architect: SVA
Anticipated Completion: Fall 2023
Project Website
Additional information and past newsletters can be found on the project website. To receive an email of this monthly newsletter or ask a project question, please email: askfacilities@wccusd.net
Storm Drain System
New swale and drain box
Blacktop
Installing new basketball back stops