Riverside ES Critical Needs Project
July 2023
Project Updates - July 2023
Construction Completed Last Month
- Mobilization
- Demolition of the project work zone and initial trenching
- Construction of the concrete curb formwork for the new play structures
- Relocation, repair, and replacement of irrigation piping, controllers, and valves
Upcoming Activities
- Grading
- Installing storm drain lines
- Pouring the concrete curbs and establishing sub base for the safety surface
Project Overview
- Project Scope: Adjusting the primary playground to relocate the kindergarten playground and garden, which were displaced during the soil stabilization project. The project includes the installation of two play structures, and repair/replacement of the blacktop surface, and constructing a garden.
- Architect: SVA
Anticipated Completion: Fall 2023
Project Website
Additional information and past newsletters can be found on the project website. To receive an email of this monthly newsletter or ask a project question, please email: askfacilities@wccusd.net
Irrigation
Installation of new valves
Site Prep
Trenching for the new storm drain line and grading of blacktop area