SHANNON ES - MPR Project
August 2024
Project Updates - August 2024
Construction Completed Last Month
- Demolition of existing asphalt
- Soil preparation for building foundations
- Installation of the temporary emergency vehicle access road
- Begin installation of site utilities (while the parking lot has been closed for this activity, it will reopen for the first day of school)
Construction Work Planned for This Month
- Building Foundations
- Underground Utilities
- Asphalt paving and striping at the parking lot
Project Overview
- Project Scope: The primary purpose of this project is to build a new multi purpose room with dining area, stage, and food services kitchen, servery, and support spaces. After the completion of the new building, the existing cafeteria portable will be removed. The project will include roll-up doors to support connection to the exterior, landscaping around the building, and infrastructure for a new garden. This project is an investment in our community through the use of taxpayer bond dollars.
- Architect: Hamilton + Aitken Architects
- Anticipated Completion: Fall/Winter 2025
Project Website
Additional information and past newsletters can be found on the project website. To receive an email of this monthly newsletter or ask a project question, please email: askfacilities@wccusd.net
Preparing for building footings
The trenches indicate the rough outline of the new dining area, raised stage, and kitchen