Hercules CNP
August 2023
Project Updates - August 2023
Welcome Back!
Accessibility improvements are in process for the Middle School Drop Off. The first phase of improvements will be completed and the drop-off will be open for the first day of school.
Underground utility trenches outside the project site were also completed to limit disruption on campus during the school year.
Construction Completed Last Month
- Middle School drop-off accessibility improvements
- Rough grading of the new building site
- Conduit pathway from the project site to other areas on campus to connect to the main electrical and data services
Upcoming Activities
- Continued preparation of the building pad subgrade
- Excavation of building footings and underground utility trenches within the project site
Project Overview
- Project Scope: The primary purpose of this project is to build eight permanent high-quality science labs for both the Middle and High Schools. This project was identified in the Facilities Master Plan as Critical Needs Project. Support spaces include science teacher workrooms and student and staff restrooms. By the end of the project, nine portables will be removed from the campuses.
- Architect: DSK Architects
- Contractor: Soltek Pacific Construction
- Anticipated Completion: Summer 2024
Project Website
Additional information and past newsletters can be found on the project website. To receive an email of this monthly newsletter or ask a project question, please email: askfacilities@wccusd.net
Project Site
Removal of soil and grading
Site Investigation
Survey and existing utility investigation