Project Updates - April 2024
Construction Completed Last Month
- Continue framing on the High School side
- Installed glulam beams and start roof framing on the High School side
- Roof framing completed on the Middle School side and ongoing on the High School side
- Ongoing electrical and plumbing rough-in on the Middle School side
Construction Work Planned for This Month
- Placing wall insulation and applying the plywood for the sheer walls
- Continue installing roofing
- Applying the exterior waterproofing
- Ongoing electrical, HVAC, and plumbing rough-in
- Continue installing scaffolding to prepare for exterior stucco
- Install drywall
Project Overview
- Project Scope: The primary purpose of this project is to build eight permanent high-quality science labs for both the Middle and High Schools. This project was identified in the Facilities Master Plan as a Critical Needs Project. Support spaces include science teacher workrooms and student and staff restrooms. By the end of the project, nine portables will be removed from the campuses.
- Architect: DSK Architects
- Contractor: Soltek Pacific Construction
- Anticipated Completion: Fall / Winter 2024