Lake ES -School Replacement Project
April 2024
Project Updates - April 2024
Construction Activity
Building A - Office and Library
Ongoing work in Progress:
- Interior door hardware
- Wood Ceiling in the main office
- Finishing touches on casework
- Installing rubber base
- Installing operable partition in the Library and Community Room
Building B and C - Classroom Buildings
Ongoing work in Progress:
- Interior doors and hardware
- Finishing touches on casework
- Installing rubber base
- Installing operable partitions in the Classrooms and Project Room
- Installing acoustical paneling
Site Work
- Installing concrete sidewalks around the front entryway
- Ongoing installation of perimeter fencing
- Pave the emergency access road and student drop-off
Project Overview
- Project Scope: The primary purpose of this project is to replace the school campus. Campus will be occupied during the duration of this project. The project will have two main construction phases. The first phase will include new buildings and site work on the East half of the campus and the second phase will include new buildings and remaining site work on the West half of the campus. Project design started in August 2021 and the first phase of construction is scheduled to start in Summer 2022. Construction for Phase 1 is scheduled through Summer of 2023 and Phase 2 is scheduled through Fall 2025. This project is an investment in our community through the use of taxpayer bond dollars.
- Architect: Quattrocchi Kwok Architects - QKA
- Anticipated Completion: Fall 2025
Project Website
Additional information and past newsletters can be found on the project website. To receive an email of this monthly newsletter or ask a project question, please email: askfacilities@wccusd.net
Flex Area
Wood ceiling and clerestory window
Flex Area
Study nooks