Collins ES Critical Needs Project
April 2024
Project Updates - April 2024
New Heating, Ventilation and Air Conditioning (HVAC) equipment is operational!
A new transformer and PG&E electrical service was installed allowing the HVAC equipment to be powered up over spring break.
Next Steps:
- Complete commissioning and programming of the control system
- Remove boiler systems in the classroom wings over summer break
Project Overview
- Project Scope: Improvements to site HVAC Systems, Electrical Infrastructure, and Accessibility including path of travel improvements and parking lot updates.
-
Architect: PBK Architects
Anticipated Completion: Spring 2024